In a dispute between PIK Management Company and TriumfStroy, the courts worked out a net balance without first deciding several of the contractor’s counterclaims. The Supreme Court sent those claims, the set-off and costs back to the Moscow Commercial Court. It did not award the disputed amounts.
What was missing · Why the balance could change
What was missing
The customer wanted its unused advance back after terminating contracts for residential construction in St Petersburg. The contractor’s claim for the value of completed work was only one part of its response. It also challenged terms of the contracts and sought, among other items, payment for materials and compensation for property it said had not been returned.
The lower courts examined the claim for completed work, then rejected other claims without assessing the evidence supporting them. A right to request a supplemental judgment did not relieve the courts of the obligation to deal with those claims.
Why the balance could change
An amount due for work and an amount due for materials can depend on different documents. In this dispute the missing findings affected the calculation of the balance: subtracting the awards from one another could not resolve a claim the court had never examined. The Supreme Court announced its decision on 18 November 2026; the full ruling is dated 20 November.
Must the trial court rehear the entire contract dispute?
No. The order lists the matters remitted, including the set-off and allocation of costs. The other parts of the judgments stand. On remand, each outstanding claim still needs evidence of its basis and amount.